Milestones

  • Public consultation

    19th October 2021

     

    -

     

    13th December 2021

    Collecting your views on the draft Smithfield Riverside Strategic Development Framework
  • Analysis

    13th December 2021

     

    -

     

    30th January 2022

    Analysis of all the feedback received will be undertaken and considered by the project team.
  • Refined masterplan

    July 2021

     

    -

     

    October 2021

    Changes will be made to the document as the feedback is considered.
  • Cabinet approval

    16th February

     

    -

     

    End date

    Shropshire Council's Cabinet will consider the consultation feedback report and the amended Strategic Development Framework.
  • Final masterplan

    26th February 2022

     

    -

     

    Upcoming

    Once Cabinet has approved the final masterplan, it will not need to go to full Council. Cabinet will approve for publication. (Note: this is a change - it was previously anticipated Council sign off may be required).