Collecting your views on the draft Smithfield Riverside Strategic Development Framework
Analysis
13th December 2021
-
30th January 2022
Analysis of all the feedback received will be undertaken and considered by the project team.
Refined masterplan
July 2021
-
October 2021
Changes will be made to the document as the feedback is considered.
Cabinet approval
16th February
-
End date
Shropshire Council's Cabinet will consider the consultation feedback report and the amended Strategic Development Framework.
Final masterplan
26th February 2022
-
Upcoming
Once Cabinet has approved the final masterplan, it will not need to go to full Council. Cabinet will approve for publication. (Note: this is a change - it was previously anticipated Council sign off may be required).